EU agrees faster permits for EV charging, grids and storage
Stand-alone charging stations will need approval within six months under the provisional deal, while smaller installations on existing structures will be exempt from administrative permits.
The European Parliament and the Council have reached a provisional agreement to speed up permitting for renewable energy projects, electricity grids, storage facilities and electric vehicle (EV) charging stations, as part of the European grids package proposed by the Commission in December 2025.
Under the deal, permits for stand-alone storage and charging stations must be granted within six months. No administrative permits will be required to install charging stations with a total capacity of up to 1 MW on artificial structures, while the permit threshold for small-scale solar, storage and recharging installations rises from 100 kW to 200 kW.
Solar equipment and co-located storage will need to be approved within three months, and pumped hydropower storage within two years. Grid connections must be granted within three months, or six if duly justified. Member states will also have to set up a single digital portal covering all permitting steps.
The agreement strengthens the presumption that renewable energy and grid projects are of overriding public interest, which member states may only set aside in justified cases involving cultural heritage or security and defence. Projects above 7 MW will have to share economic benefits with local communities.
“We took a very important step tonight to make sure that we get a faster rollout of renewables and grid infrastructure, to the benefit of our citizens, to mitigate climate change and to boost our competitiveness,” said lead MEP Niels Fuglsang.
The text must now be approved by Parliament’s Industry, Research and Energy committee, endorsed by the full Parliament and the Council, and published in the Official Journal before entering into force.